(a) Authorization is granted for the Level III
rehabilitation construction projects identified in this section,
subject to the general conditions specified in W.S. 99-3-104.
Source notes for subsection (a): (Laws 2004, Ch. 118, § 1.)
(b) Project – Albin Pipelines and Well Rehabilitation:
(i) Project sponsor: Town of Albin;
(ii) Project purpose: Municipal, rural domestic water
supply;
(iii) Project description: Rehabilitation of
existing wells and construction of a new pipeline from the
Station Well to their 100,000 gallon elevated storage tank and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Four hundred thirty
thousand dollars ($430,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering, and construction of the
project an amount not to exceed two hundred fifteen thousand
dollars ($215,000.00) or fifty percent (50%) of the actual
development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two hundred fifteen
thousand dollars ($215,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2013; and
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources.
Source notes for subsection (b): (Laws 2004, Ch. 118, § 1;
2008, Ch. 75, § 2; 2011, Ch. 63, § 2.)
(c) Project – Casper Alcova Rehabilitation Project:
(i) Project sponsor: Casper Alcova Irrigation
District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Repair and replacement of
aged open ditch drop structures with new drop structures and
headwalls, replacement of open ditches with plastic pipe and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: One million seven hundred
sixty thousand dollars ($1,760,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed eight hundred eighty thousand dollars ($880,000.00) or
one hundred percent (100%) of the cost of the materials,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission eight hundred eighty
thousand dollars ($880,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010;
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources;
(viii) Supplemental project budget: Four hundred
forty thousand dollars ($440,000.00);
(ix) Supplemental project grant: The state of Wyoming
shall grant to the sponsor from water development account II
through the commission an amount not to exceed two hundred
ninety-four thousand eight hundred dollars ($294,800.00) for the
purchase of one hundred percent (100%) of project materials
costs as supported by vendor invoices and approved by the
commission;
(x) Supplemental appropriation: There is appropriated
from water development account II to the commission an
additional two hundred ninety-four thousand eight hundred
dollars ($294,800.00), which when combined with the original
appropriation, as described in paragraphs (iv) through (vi) of
this subsection, total one million one hundred seventy-four
thousand eight hundred dollars ($1,174,800.00), or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2010;
and
(xi) Special supplemental conditions:
(A) The sponsor is responsible for acquiring all
necessary easements and permits and the remaining thirty-three
percent (33%) of the total supplemental project budget from
other sources which shall include all labor and equipment costs
associated with completing the project;
(B) The supplemental appropriation is based upon
a different grant and loan ratio than the original
appropriation. The original funding described in paragraphs
(iv) through (vi) of this subsection shall be expended prior to
incurring supplemental funding expenditures.
Source notes for subsection (c): (Laws 2004, Ch. 118, § 1;
2005, ch. 147, § 12; 2006, ch. 105, § 10.)
(d) Project – Gillette Madison and Pine Ridge Tanks
Project:
(i) Project sponsor: City of Gillette;
(ii) Project purpose: Municipal water supply;
(iii) Project description: Design and construction
of new, redundant water storage tanks that are needed to
facilitate maintenance of the existing storage tanks and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: One million one hundred
thousand dollars ($1,100,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed five hundred fifty thousand
dollars ($550,000.00) or fifty percent (50%) of the actual
development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission five hundred fifty
thousand dollars ($550,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2008; and
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources.
Source notes for subsection (d): (Laws 2004, Ch. 118, § 1.)
(e) Project – Glenrock Sunup Ridge Tank Rehabilitation
Project:
(i) Project sponsor: Town of Glenrock;
(ii) Project purpose: Municipal water supply;
(iii) Project description: Rehabilitation of the
town’s Sunup Ridge tank and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: Two hundred sixty-five
thousand five hundred dollars ($265,500.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed one hundred thirty-two thousand
seven hundred fifty dollars ($132,750.00) or fifty percent (50%)
of the actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one hundred thirty-two
thousand seven hundred fifty dollars ($132,750.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2008;
and
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources.
Source notes for subsection (e): (Laws 2004, Ch. 118, § 1.)
(f) Project – Guernsey Tanks and Pipelines Project:
(i) Project sponsor: Town of Guernsey;
(ii) Project purpose: Municipal water supply;
(iii) Project description: The project will
rehabilitate the town’s water storage facilities, provide for an
emergency connection to the Wyoming Army National Guard Camp,
replace undersized and aged transmission mains and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: One million two hundred
thirty thousand dollars ($1,230,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed six hundred fifteen thousand
dollars ($615,000.00) or fifty percent (50%) of the actual
development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission six hundred fifteen
thousand dollars ($615,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2008; and
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources.
Source notes for subsection (f): (Laws 2004, Ch. 118, § 1.)
(g) Project – Heart Mountain Pipe Conversion Project:
(i) Project sponsor: Heart Mountain Irrigation
District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: The project will replace
open ditch laterals with piped laterals and includes the
replacement of ditch turnouts, head gates and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: One million two hundred
four thousand two hundred twenty dollars ($1,204,220.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed six hundred two thousand one hundred ten dollars
($602,110.00) or one hundred percent (100%) of the cost of the
materials, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission six hundred two
thousand one hundred ten dollars ($602,110.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2010;
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources;
(viii) Supplemental project budget: One hundred
sixty-nine thousand dollars ($169,000.00);
(ix) Supplemental project grant: The state of Wyoming
shall grant to the sponsor from water development account II
through the commission an amount not to exceed one hundred
thirteen thousand two hundred thirty dollars ($113,230.00) for
the purchase of one hundred percent (100%) of project material
costs as supported by vendor invoices and approved by the
commission or sixty-seven percent (67%) of the total
supplemental project costs, whichever is less;
(x) Supplemental appropriation: There is appropriated
from water development account II to the commission an
additional one hundred thirteen thousand two hundred thirty
dollars ($113,230.00), which when combined with the original
appropriation as described in paragraphs (iv) through (vi) of
this subsection, total seven hundred fifteen thousand three
hundred forty dollars ($715,340.00), or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010; and
(xi) Special supplemental conditions:
(A) The sponsor is responsible for acquiring all
necessary easements and permits and the remaining thirty-three
percent (33%) of the total supplemental project budget from
other sources which shall include all labor and equipment costs
associated with completing the project;
(B) The supplemental appropriation is based upon
a different grant percentage than the original appropriation.
The original funding described in paragraphs (iv) through (vi)
of this subsection shall be expended prior to incurring
supplemental funding expenditures.
Source notes for subsection (g): (Laws 2004, Ch. 118, § 1;
2006, ch. 105, § 11.)
(h) Project – Hidden Valley Pipelines Project:
(i) Project sponsor: Midvale Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: The project entails
replacing open ditches with piped laterals and miscellaneous
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Three million four
hundred twenty-six thousand three hundred four dollars
($3,426,304.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed one million four hundred seventy-four thousand one
hundred three dollars ($1,474,103.00) or one hundred percent
(100%) of the cost of the materials, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one million four
hundred seventy-four thousand one hundred three dollars
($1,474,103.00) or as much thereof as is necessary to carry out
the purpose of this subsection. Unexpended funds appropriated
under this subsection shall revert to water development account
II on July 1, 2010;
(vii) Special condition: The sponsor is responsible
for acquiring the balance of the total project budget from other
sources;
(viii) Supplemental project budget: Two million two
hundred thirty-two thousand dollars ($2,232,000.00);
(ix) Supplemental project grant: The state of Wyoming
shall grant to the sponsor from water development account II
through the commission an amount not to exceed one million four
hundred ninety-five thousand four hundred forty dollars
($1,495,440.00) for the purchase of one hundred percent (100%)
of project material costs as supported by vendor invoices and
approved by the commission or sixty-seven percent (67%) of the
total supplemental project costs, whichever is less;
(x) Supplemental appropriation: There is appropriated
from water development account II to the commission an
additional one million four hundred ninety-five thousand four
hundred forty dollars ($1,495,440.00), which when combined with
funds appropriated as described in paragraphs (iv) through (vi)
of this subsection, total two million nine hundred sixty-nine
thousand five hundred forty-three dollars ($2,969,543.00), or as
much thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2010;
and
(xi) Special supplemental conditions:
(A) The sponsor is responsible for acquiring all
necessary easements and permits and the remaining thirty-three
percent (33%) of the total supplemental project budget from
other sources which shall include all labor and equipment costs
associated with completing the project;
(B) The supplemental appropriation is based upon
a different grant percentage than the original appropriation.
The original funding described in paragraphs (iv) through (vi)
of this subsection shall be expended prior to incurring
supplemental funding expenditures.
Source notes for subsection (h): (Laws 2004, Ch. 118, § 1;
2006, ch. 105, § 12.)
(j) Project – Lake Hattie Dam Rehabilitation Project:
(i) Project sponsor: Pioneer Canal-Lake Hattie
Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Replacing the existing
head gates with a new structure designed to address sediment
buildup at the head gates and appurtenances for the project to
function in the manner intended;
(iv) Total project budget: One hundred sixty-three
thousand dollars ($163,000.00);
(v) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed eighty-one thousand five hundred
dollars ($81,500.00) or fifty percent (50%) of the actual
development costs, whichever is less, for a term of thirty (30)
years from the date the commission determines project benefits
accrue to the sponsor, at an annual rate of six percent (6%);
(vi) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed eighty-one thousand five hundred
dollars ($81,500.00) or fifty percent (50%) of the actual
development costs, whichever is less; and
(vii) Appropriation: There is appropriated from water
development account II to the commission one hundred sixty-three
thousand dollars ($163,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010.
Source notes for subsection (j): (Laws 2004, Ch. 118, § 1.)
(k) Project – Saratoga Standpipe Rehabilitation Project:
(i) Project sponsor: The Town of Saratoga and the
Carbon County Impact Joint Powers Board;
(ii) Project purpose: Municipal water supply;
(iii) Project description: Rehabilitation of the
existing water storage tank and appurtenances necessary to make
the project function in the manner intended;
(iv) Total project budget: Four hundred thousand
dollars ($400,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed two hundred thousand dollars
($200,000.00) or fifty percent (50%) of the actual development
costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two hundred thousand
dollars ($200,000.00) or as much thereof as is necessary to
carry out the purpose of this subsection. Unexpended funds
appropriated under this subsection shall revert to water
development account II on July 1, 2008; and
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the balance of the total
project budget from other sources.
Source notes for subsection (k): (Laws 2004, Ch. 118, § 1.)
(m) Project – Turnerville Water Supply Project:
(i) Project sponsor: Turnerville Water and Sewer
District;
(ii) Project purpose: Municipal, rural domestic water
supply;
(iii) Project description: Replacing undersized and
aged transmission pipelines, spring rehabilitation, construction
of a water storage tank and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: One million one hundred
seventy-five thousand five hundred dollars ($1,175,500.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed five hundred eighty-seven
thousand seven hundred fifty dollars ($587,750.00) or fifty
percent (50%) of the actual development costs, whichever is
less;
(vi) Appropriation: There is appropriated from water
development account II to the commission five hundred eighty-
seven thousand seven hundred fifty dollars ($587,750.00) or as
much thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2010;
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the balance of the total
project budget from other sources;
(viii) Supplemental project budget: Two hundred
thirty-three thousand two hundred dollars ($233,200.00);
(ix) Supplemental project grant: The state of Wyoming
shall grant to the sponsor from water development account II
through the commission an amount not to exceed one hundred
fifty-six thousand two hundred forty-four dollars ($156,244.00)
or sixty-seven percent (67%) of the additional funds needed to
complete the project, whichever is less. Supplemental grant
funds may be used for design, construction engineering and
construction of the project;
(x) Supplemental appropriation: There is appropriated
from water development account II to the commission an
additional one hundred fifty-six thousand two hundred forty-four
dollars ($156,244.00), which when combined with the original
appropriation, as described in paragraphs (iv) through (vi) of
this subsection, total seven hundred forty-three thousand nine
hundred ninety-four dollars ($743,994.00), or as much thereof as
is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010; and
(xi) Special supplemental conditions:
(A) The sponsor is responsible for acquiring the
remaining thirty-three percent (33%) of the total supplemental
project budget from other sources;
(B) The supplemental appropriation is based upon
a different grant percentage than the original appropriation.
The original funding described in paragraphs (iv) through (vi)
of this subsection shall be expended prior to incurring
supplemental funding expenditures.
Source notes for subsection (m): (Laws 2004, Ch. 118, § 1;
2006, ch. 105, § 14.)
(n) Project - Wind River Irrigation Project:
(i) Project sponsor: The Joint Business Council for
the Eastern Shoshone and Northern Arapaho Tribes or the Eastern
Shoshone Business Council or the Northern Arapaho Business
Council;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: The rehabilitation of the
irrigation delivery system and appurtenances necessary to make
the project function in the manner intended;
(iv) Total project budget: Seven million dollars
($7,000,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering, and construction of the
project an amount not to exceed three million five hundred
thousand dollars ($3,500,000.00) or fifty percent (50%) of the
actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission three million five
hundred thousand dollars ($3,500,000.00) or as much thereof as
is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2015; and
(vii) Special conditions:
(A) The sponsor is responsible for acquiring
fifty percent (50%) of the total project budget from other
sources;
(B) In the event of a dispute between the
contract parties, unexpended funds shall be withheld until the
dispute is resolved.
Source notes for subsection (n): (Laws 2004, Ch. 118, § 1;
2007, Ch. 121, § 2; 2010, ch. 68, § 2.)
Nearby Sections
15
Cite This Page — Counsel Stack
Wyoming § 99-3-904, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/3/99-3-904.