(a) Authorization is granted for the Level III
rehabilitation construction projects identified in this section,
subject to the general conditions specified in W.S. 99-3-104.
Source notes for subsection (a): (Laws 2006, Ch. 105, § 3.)
(b) Project – Alpine Wells Rehabilitation:
(i) Project sponsor: The Town of Alpine;
(ii) Project purpose: Municipal water supply;
(iii) Project description: Design and installation of
new pumps, pipelines and a backup power supply and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: Five hundred thirty-seven
thousand dollars ($537,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering, and construction of the
project an amount not to exceed three hundred fifty-nine
thousand seven hundred ninety dollars ($359,790.00) or sixty-
seven percent (67%) of the actual development costs, whichever
is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission three hundred fifty-
nine thousand seven hundred ninety dollars ($359,790.00) or as
much thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2013;
and
(vii) Special condition: The sponsor is responsible
for acquiring thirty-three percent (33%) of the total project
budget from other sources.
Source notes for subsection (b): (Laws 2006, Ch. 105, § 3;
2011, Ch. 63, § 2.)
(c) Project – Big Valley and Crossed Arrows Water Supply:
(i) Project sponsor: Big Valley and Crossed Arrows
Improvement District;
(ii) Project purpose: Rural, domestic water supply;
(iii) Project description: Design and installation of
transmission pipelines, storage facilities and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: One million one hundred
thirteen thousand dollars ($1,113,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering, and construction of the
project an amount not to exceed seven hundred forty-five
thousand seven hundred ten dollars ($745,710.00) or sixty-seven
percent (67%) of the actual development costs, whichever is
less;
(vi) Appropriation: There is appropriated from water
development account II to the commission seven hundred forty-
five thousand seven hundred ten dollars ($745,710.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on March 1, 2007;
and
(vii) Special conditions:
(A) The sponsor is responsible for acquiring
thirty-three percent (33%) of the total project budget from
other sources;
(B) The sponsor shall enter into a water service
contract with the Town of Meeteetse before the project
commences.
Source notes for subsection (c): (Laws 2006, Ch. 105, § 3;
2007, Ch. 121, § 2.)
(d) Project – Frannie Raw Water Supply:
(i) Project sponsor: Town of Frannie;
(ii) Project purpose: Municipal raw water supply;
(iii) Project description: Rehabilitation of the
town's irrigation well and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: Six hundred fifty-five
thousand dollars ($655,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering, and construction of the
project an amount not to exceed four hundred thirty-eight
thousand eight hundred fifty dollars ($438,850.00) or sixty-
seven percent (67%) of the actual development costs, whichever
is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed two hundred sixteen thousand one
hundred fifty dollars ($216,150.00) or thirty-three percent
(33%) of the actual development costs, whichever is less, for a
term of twenty (20) years from the date the commission
determines project benefits accrue to the sponsor, at an annual
rate of four percent (4%); and
(vii) Appropriation: There is appropriated from water
development account II to the commission six hundred fifty-five
thousand dollars ($655,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on March 1, 2007.
Source notes for subsection (d): (Laws 2006, Ch. 105, § 3;
2007, Ch. 121, § 2.)
(e) Project – Hopkins Producers Supply Project:
(i) Project sponsor: Hopkins Producers Irrigation
District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of new gravity flow pipelines to replace open ditch laterals and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: One million fifty
thousand dollars ($1,050,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed seven hundred three thousand
five hundred dollars ($703,500.00) or sixty seven percent (67%)
of the actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission seven hundred three
thousand five hundred dollars ($703,500.00) or as much thereof
as is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010; and
(vii) Special condition: The sponsor is responsible
for acquiring thirty-three percent (33%) of the balance of the
total project budget from other sources.
Source notes for subsection (e): (Laws 2006, Ch. 105, § 3.)
(f) Project – Laramie Water Management Project (meters):
(i) Project sponsor: City of Laramie;
(ii) Project purpose: Municipal water supply;
(iii) Project description: The rehabilitation and
replacement of water transmission meters and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: One hundred forty-five
thousand dollars ($145,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed ninety-seven thousand one
hundred fifty dollars ($97,150.00) or sixty-seven percent (67%)
of the actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission ninety-seven thousand
one hundred fifty dollars ($97,150.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010; and
(vii) Special condition: The sponsor is responsible
for acquiring thirty-three percent (33%) of the total project
budget from other sources.
Source notes for subsection (f): (Laws 2006, Ch. 105, § 3.)
(g) Project – Midvale Irrigation District
Conservation/Automation Project:
(i) Project sponsor: Midvale Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and installation of
system monitoring and automation equipment and appurtenances
necessary for the project to function in the manner intended;
(iv) Total project budget: Eight hundred ten
thousand dollars ($810,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed five hundred forty-two thousand seven hundred dollars
($542,700.00) or one hundred percent (100%) of the materials
cost, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission five hundred forty-two
thousand seven hundred dollars ($542,700.00) or as much thereof
as is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2012; and
(vii) Special condition: The sponsor is responsible
for retaining professional engineering services to design the
project, compile materials and bidding documents, and monitor
construction activities including the installation of project
components and the tracking of project expenditures.
Source notes for subsection (g): (Laws 2006, Ch. 105, § 3;
2010, ch. 68, § 2.)
(h) Project – Shoshone Eagle Nest Creek:
(i) Project sponsor: Shoshone Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: To design and construct
repairs to the Eagle Nest Creek crossing and replace open ditch
laterals with piped laterals and appurtenances necessary to make
the project function in the manner intended;
(iv) Total project budget: One million seven hundred
ten thousand dollars ($1,710,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed one million one hundred forty-five thousand seven hundred
dollars ($1,145,700.00) or one hundred percent (100%) of the
materials cost, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one million one hundred
forty-five thousand seven hundred dollars ($1,145,700.00) or as
much thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2010;
and
(vii) Special conditions: The sponsor is responsible
for retaining professional engineering services to design the
project, compile materials bidding documents, and monitor
construction activities including the installation of project
components and the tracking of project expenditures.
Source notes for subsection (h): (Laws 2006, Ch. 105, § 3.)
(j) Project – Thermopolis Storage Replacement and
Rehabilitation:
(i) Project sponsor: The Town of Thermopolis;
(ii) Project purpose: Municipal, domestic water
supply;
(iii) Project description: Rehabilitation of the
town's water storage system and appurtenances necessary to make
the project function in the manner intended;
(iv) Total project budget: Two million eight hundred
eighty thousand dollars ($2,880,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed one million nine hundred twenty-
nine thousand six hundred dollars ($1,929,600.00) or sixty-seven
percent (67%) of the actual development costs, whichever is
less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two million three
hundred twenty-four thousand one hundred sixty dollars
($2,324,160.00) or as much thereof as is necessary to carry out
the purpose of this subsection. Unexpended funds appropriated
under this subsection shall revert to water development account
II on July 1, 2012;
(vii) Special condition: The sponsor is responsible
for acquiring nineteen and three-tenths percent (19.3%) of the
total project budget from other sources; and
(viii) Project loan: The state of Wyoming shall loan
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed three hundred ninety-four
thousand five hundred sixty dollars ($394,560.00) or thirteen
and seven-tenths percent (13.7%) of the actual development
costs, whichever is less, for a term of thirty (30) years from
the date the commission determines project benefits accrue to
the sponsor, at an annual rate of four percent (4%).
Source notes for subsection (j):(Laws 2006, Ch. 105, § 3; 2008,
Ch. 75, § 2.)
(k) Project – Wamsutter Water Supply Rehabilitation:
(i) Project sponsor: Town of Wamsutter;
(ii) Project purpose: Municipal water supply;
(iii) Project description: Relocation and
reconstruction of an existing storage tank, construction of a
new pump station, transmission pipeline and appurtenances
necessary for the project to function in the manner intended;
(iv) Total project budget: Five hundred seventeen
thousand dollars ($517,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed two hundred fifty-eight thousand
five hundred dollars ($258,500.00) or fifty percent (50%) of the
actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two hundred fifty-eight
thousand five hundred dollars ($258,500.00) or as much thereof
as is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010; and
(vii) Special conditions:
(A) The sponsor is responsible for acquiring
fifty percent (50%) of the total project budget from other
sources;
(B) The sponsor will receive a seventy thousand
dollar ($70,000.00) credit, which represents the value of an
existing steel tank that has been donated to the town, when
computing their required funding match.
Source notes for subsection (k): (Laws 2006, Ch. 105, § 3.)
(m) Project – Wheatland Irrigation District Re-regulation
Reservoirs:
(i) Project sponsor: Wheatland Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: To construct re-
regulation reservoirs and appurtenances necessary for the
project to function in the manner intended;
(iv) Total project budget: Two hundred twenty-four
thousand dollars ($224,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials and engineering
design and construction services as supported by vendor invoices
and approved by the commission an amount not to exceed one
hundred fifty thousand eighty dollars ($150,080.00) or one
hundred percent (100%) of the materials and engineering design
and construction services cost, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one hundred fifty
thousand eighty dollars ($150,080.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2010; and
(vii) Special condition: The sponsor is responsible
for acquiring all necessary easements and permits and thirty-
three percent (33%) of the total project budget from other
sources which shall include all labor and equipment costs
associated with completing the project.
Source notes for subsection (m): (Laws 2006, Ch. 105, § 3.)
(n) Project – Worland Eastside Transmission Line:
(i) Project sponsor: The City of Worland;
(ii) Project purpose: Municipal water supply;
(iii) Project description: Replacement of a portion
of the city's eastside transmission line and appurtenances
necessary for the project to function in the manner intended;
(iv) Total project budget: Five million three
hundred thousand dollars ($5,300,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, construction
engineering, project land procurement and construction of the
project an amount not to exceed two million six hundred fifty
thousand dollars ($2,650,000.00) or fifty percent (50%) of the
actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two million six hundred
fifty thousand dollars ($2,650,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2014; and
(vii) Special condition: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources.
Source notes for subsection (n): (Laws 2006, Ch. 105, § 3;
2009, Ch. 38, § 2.)