(a) Authorization is granted for the Level III
rehabilitation construction projects identified in this section
subject to the general conditions specified in W.S. 99-3-104,
provided that W.S. 99-3-104(a)(iii) shall not apply to the
projects identified in this section unless required by W.S. 41-
2-121. Source Notes for subsection (a): (Laws 2022, Ch. 93, §
1.)
(b) Project – Big Horn Canal Adobe Check Structure 2022:
(i) Project sponsor: Big Horn Canal Irrigation
District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
a water control structure and appurtenances necessary to make
the project function in the manner intended;
(iv) Total project budget: two hundred thirty
thousand dollars ($230,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one hundred fifty-four thousand
one hundred dollars ($154,100.00) or sixty-seven percent (67%)
of these actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one hundred fifty-four
thousand one hundred dollars ($154,100.00) or as much thereof as
is necessary to carry out the purpose of this subsection.
Unexpended and unobligated funds appropriated under this
subsection shall revert to water development account II on July
1, 2027;
(vii) Special Conditions: The sponsor is responsible
for acquiring thirty-three percent (33%) of the total project
budget from other sources. Source Notes for subsection (b):
(Laws 2022, Ch. 93, § 1.)
(c) Project – Cottonwood Irrigation District Pipeline
Replacement 2022:
(i) Project sponsor: Cottonwood Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pipelines, structures and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: one million six hundred
thousand dollars ($1,600,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one million seventy-two thousand
dollars ($1,072,000.00) or sixty-seven percent (67%) of these
actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed five hundred twenty-eight
thousand dollars ($528,000.00) or thirty-three percent (33%) of
these actual development costs, whichever is less, for a term of
forty (40) years from the date the commission determines that
project benefits accrue to the sponsor, at an annual interest
rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission one million six hundred
thousand dollars ($1,600,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended and unobligated funds appropriated under this
subsection shall revert to water development account II on July
1, 2027;
(viii) Special Conditions: The appropriation of funds
for this project is contingent upon the transfer of funds to
water development account II as described in section 3 of this
act or transfer from another funding source. Source Notes for
subsection (c): (Laws 2022, Ch. 93, § 1.)
(d) Project – Deaver ID Rehabilitation 2022:
(i) Project sponsor: Deaver Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pipelines, structures and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: two million seven hundred
twenty-two thousand seven hundred dollars ($2,722,700.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed eight hundred sixteen thousand
eight hundred ten dollars ($816,810.00) or thirty percent (30%)
of these actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission eight hundred sixteen
thousand eight hundred ten dollars ($816,810.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended and unobligated funds appropriated under
this subsection shall revert to water development account II on
July 1, 2027;
(vii) Special Conditions: The sponsor is responsible
for acquiring seventy percent (70%) of the total project budget
from other sources. Source Notes for subsection (d): (Laws
2022, Ch. 93, § 1.)
(e) Project – Dry Creek Irrigation District Pipeline
Replacement 2022:
(i) Project sponsor: Dry Creek Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pipelines, structures and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: one million eight hundred
fifty thousand dollars ($1,850,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one million two hundred thirty-
nine thousand five hundred dollars ($1,239,500.00) or sixty-
seven percent (67%) of these actual development costs, whichever
is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed six hundred ten thousand five
hundred dollars ($610,500.00) or thirty-three percent (33%) of
these actual development costs, whichever is less, for a term of
twenty (20) years from the date the commission determines that
project benefits accrue to the sponsor, at an annual interest
rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission one million eight
hundred fifty thousand dollars ($1,850,000.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended and unobligated funds appropriated under
this subsection shall revert to water development account II on
July 1, 2028;
(viii) Repealed by Laws 2023, ch. 180, § 7. Source
Notes for subsection (e): (Laws 2022, Ch. 93, § 1, 2023, Ch.
180, § 2.)
(f) Project – Goshen ID 29.4 Pipeline Project Phase II
2022:
(i) Project sponsor: Goshen Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pipelines, structures and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: four hundred eighty-five
thousand three hundred forty dollars ($485,340.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed two hundred ninety thousand dollars ($290,000.00) or
one hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two hundred ninety
thousand dollars ($290,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended and unobligated funds appropriated under this
subsection shall revert to water development account II on July
1, 2027;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures;
(C) The appropriation of funds for this project
is contingent upon the transfer of funds to water development
account II as described in section 3 of this act or transfer
from another funding source. Source Notes for subsection (f):
(Laws 2022, Ch. 93, § 1.)
(g) Project – Goshen ID Tunnel Rehabilitation 2022:
(i) Project sponsor: Goshen Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Engineering analysis,
design and pre-construction of tunnels, structures and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Four million seven hundred
ninety-five thousand nine hundred twenty dollars
($4,795,920.00). The sponsor's project budget is two million
three hundred fifty thousand dollars ($2,350,000.00) or forty-
nine percent (49%) of the total project budget, whichever is
less;
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the engineering analysis, design, permit
procurement, project land procurement, and pre-construction
engineering of the project an amount not to exceed one million
five hundred seventy-four thousand five hundred dollars
($1,574,500.00) or sixty-seven percent (67%) of these actual
development costs within the sponsor's project budget, whichever
is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the engineering analysis, design, permit
procurement, project land procurement and pre-construction
engineering of the project an amount not to exceed seven hundred
seventy-five thousand five hundred dollars ($775,500.00) or
thirty-three percent (33%) of these actual development costs
within the sponsor's project budget, whichever is less, for a
term of twenty (20) years from the date the commission
determines that project benefits accrue to the sponsor or the
commission determines the project is not likely to proceed to
construction, at an annual interest rate of four percent (4%);
(vii) Repealed by Laws 2023, ch. 180, § 7.
(viii) Appropriation: There is appropriated from
water development account II to the commission two million three
hundred fifty thousand dollars ($2,350,000.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended and unobligated funds appropriated under
this subsection shall revert to water development account II on
July 1, 2027;
(ix) Repealed by Laws 2023, ch. 180, § 7. Source
Notes for subsection (g): (Laws 2022, Ch. 93, § 1, 2023, Ch.
180, § 2.)
(h) Project – Highland Hanover ID System Improvements
2022:
(i) Project sponsor: Highland Hanover Irrigation
District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pumps, pumping facilities, improvements and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: four million six hundred
eleven thousand dollars ($4,611,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed three million eighty-nine
thousand three hundred seventy dollars ($3,089,370.00) or sixty-
seven percent (67%) of these actual development costs, whichever
is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one million five hundred twenty-
one thousand six hundred thirty dollars ($1,521,630.00) or
thirty-three percent (33%) of these actual development costs,
whichever is less, for a term of thirty (30) years from the date
the commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission four million six
hundred eleven thousand dollars ($4,611,000.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended and unobligated funds appropriated under
this subsection shall revert to water development account II on
July 1, 2027. Source Notes for subsection (h): (Laws 2022, Ch.
93, § 1.)
(j) Project – Lovell Moncur Lateral Phase II 2022:
(i) Project sponsor: Lovell Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pipelines, structures and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: one million four hundred
forty-five thousand eight hundred twenty-five dollars
($1,445,825.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed nine hundred ninety-one thousand dollars ($991,000.00)
or one hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission nine hundred ninety-one
thousand dollars ($991,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended and unobligated funds appropriated under this
subsection shall revert to water development account II on July
1, 2027;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures;
(C) The appropriation of funds for this project
is contingent upon the transfer of funds to water development
account II as described in section 3 of this act or transfer
from another funding source. Source Notes for subsection (j):
(Laws 2022, Ch. 93, § 1.)
(k) Project – Owl Creek Irrigation District System
Improvements:
(i) Project sponsor: Owl Creek Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
pumping systems, structures, pipelines, improvements and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: seven million dollars
($7,000,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed four million six hundred ninety
thousand dollars ($4,690,000.00) or sixty-seven percent (67%) of
these actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed three hundred fifty thousand
dollars ($350,000.00) or five percent (5%) of these actual
development costs, whichever is less, for a term of thirty (30)
years from the date the commission determines that project
benefits accrue to the sponsor, at an annual interest rate of
four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission five million forty
thousand dollars ($5,040,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2028;
(viii) Special Conditions: The sponsor is responsible
for acquiring twenty-eight percent (28%) of the total project
budget from other sources. Source Notes for subsection (k):
(Laws 2022, Ch. 93, § 1; 2024, Ch. 99, § 2.)
Nearby Sections
15
Cite This Page — Counsel Stack
Wyoming § 99-3-2704, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/3/99-3-2704.