(a) Authorization is granted for the Level III
rehabilitation construction projects identified in this section.
Source notes for subsection (a): (Laws 2019, Ch. 55, § 1.)
(b) Project – Austin-Wall Reservoir Rehabilitation 2019:
(i) Project sponsor: Austin-Wall Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
the replacement of reservoir outlet works and appurtenances
necessary to make the project function in the manner intended;
(iv) Total project budget: Three hundred seventy-four
thousand dollars ($374,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed two hundred fifty thousand five
hundred eighty dollars ($250,580.00) or sixty-seven percent
(67%) of the actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one hundred twenty-three
thousand four hundred twenty dollars ($123,420.00) or thirty-
three percent (33%) of the actual development costs, whichever
is less, for a term of thirty (30) years from the date the
commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission three hundred seventy-
four thousand dollars ($374,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2026;
(viii) Special conditions: The appropriation of funds
for this project is contingent upon the transfer of funds to
water development account II as described in section 3 of this
act. Source notes for subsection (b): (Laws 2019,
Ch. 55, § 1; 2024, Ch. 99, § 2.)
(c) Project – Big Horn Canal Wasteway Rehabilitation 2019:
(i) Project sponsor: Big Horn Canal Irrigation
District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
replacement wasteway/check structure and appurtenances necessary
to make the project function in the manner intended;
(iv) Total project budget: Nine hundred sixty
thousand dollars ($960,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed six hundred forty-three thousand
two hundred dollars ($643,200.00) or sixty-seven percent (67%)
of the actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed three hundred sixteen thousand
eight hundred dollars ($316,800.00) or thirty-three percent
(33%) of the actual development costs, whichever is less, for a
term of thirty (30) years from the date the commission
determines that project benefits accrue to the sponsor, at an
annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission nine hundred sixty
thousand dollars ($960,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024.
Source notes for subsection (c): (Laws 2019, Ch. 55, § 1.)
(d) Project – Bluff/Upper Bluff System Improvements 2019:
(i) Project sponsor: Bluff/Upper Bluff Irrigation
District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
replacement pumps, structure repairs and appurtenances necessary
to make the project function in the manner intended;
(iv) Total project budget: Three hundred sixty-six
thousand dollars ($366,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed two hundred forty-five thousand
two hundred twenty dollars ($245,220.00) or sixty-seven percent
(67%) of the actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed forty-five thousand seven
hundred eighty dollars ($45,780.00) or twelve and fifty-one
hundredths percent (12.51%) of the actual development costs,
whichever is less, for a term of twenty (20) years from the date
the commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission two hundred ninety-one
thousand dollars ($291,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(viii) Special conditions: The sponsor is responsible
for acquiring twenty and forty-nine hundredths percent (20.49%)
of the total project budget from other sources.
Source notes for subsection (d): (Laws 2019, Ch. 55, § 1.)
(e) Project – Cody Canal Rehabilitation 2019:
(i) Project sponsor: Cody Canal Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
lateral pipelines and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: Six hundred forty-six
thousand six hundred forty-nine dollars ($646,649.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed three hundred forty-four thousand dollars
($344,000.00) or one hundred percent (100%) of the approved
materials costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission three hundred forty-
four thousand dollars ($344,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures.
Source notes for subsection (e): (Laws 2019, Ch. 55, § 1.)
(f) Project – Deaver Irrigation District Rehabilitation
2019:
(i) Project sponsor: Deaver Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
lateral pipelines and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: Eight hundred ninety-nine
thousand nine hundred twenty-nine dollars ($899,929.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed four hundred twenty-four thousand dollars
($424,000.00) or one hundred percent (100%) of the approved
materials costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission four hundred twenty-
four thousand dollars ($424,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures.
Source notes for subsection (f): (Laws 2019, Ch. 55, § 1.)
(g) Project – Dry Creek Irrigation District Rehabilitation
2019:
(i) Project sponsor: Dry Creek Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
replacement lateral pipelines and appurtenances necessary to
make the project function in the manner intended;
(iv) Total project budget: One million six hundred
twenty-eight thousand dollars ($1,628,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one million ninety thousand
seven hundred sixty dollars ($1,090,760.00) or sixty-seven
percent (67%) of the actual development costs, whichever is
less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed five hundred thirty-seven
thousand two hundred forty dollars ($537,240.00) or thirty-three
percent (33%) of the actual development costs, whichever is
less, for a term of twenty (20) years from the date the
commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission one million six hundred
twenty-eight thousand dollars ($1,628,000.00) or as much thereof
as is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(viii) Special conditions: The appropriation of funds
for this project is contingent upon the transfer of funds to
water development account II as described in section 3 of this
act.
Source notes for subsection (g): (Laws 2019, Ch. 55, § 1.)
(h) Project – Eden Valley Irrigation District System
Improvements 2019:
(i) Project sponsor: Eden Valley Irrigation and
Drainage District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
sandtrap structure and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: One million four hundred
four thousand dollars ($1,404,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed three hundred fifty-one thousand
dollars ($351,000.00) or twenty-five percent (25%) of the actual
development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission three hundred fifty-one
thousand dollars ($351,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2028;
(vii) Special conditions:
(A) The sponsor is responsible for acquiring
seventy-five percent (75%) of the total project budget from
other sources;
(B) The appropriation of funds for this project
is contingent upon the transfer of funds to water development
account II as described in section 3 of this act. Source notes
for subsection (h): (Laws 2019, Ch. 55, § 1; 2024, Ch. 99, § 2;
2025, Ch. 111, § 2.)
(j) Project – Interstate Diversion Structure
Rehabilitation 2019:
(i) Project sponsor: Interstate Irrigation and
Reservoir Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
a replacement diversion structure and appurtenances necessary to
make the project function in the manner intended;
(iv) Total project budget: Four hundred twenty
thousand dollars ($420,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed two hundred eighty-one thousand
four hundred dollars ($281,400.00) or sixty-seven percent (67%)
of the actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one hundred thirty-eight
thousand six hundred dollars ($138,600.00) or thirty-three
percent (33%) of the actual development costs, whichever is
less, for a term of twenty (20) years from the date the
commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission four hundred twenty
thousand dollars ($420,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2026.
Source Notes for subsection (j): (Laws 2024, Ch. 99, § 2.)
(k) Project – Lakeview Carter Creek Siphon/Spillway 2019:
(i) Project sponsor: Lakeview Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
a siphon/spillway structure and appurtenances necessary to make
the project function in the manner intended;
(iv) Total project budget: Three hundred fifty-one
thousand dollars ($351,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed two hundred thirty-five thousand
one hundred seventy dollars ($235,170.00) or sixty-seven percent
(67%) of the actual development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one hundred fifteen thousand
eight hundred thirty dollars ($115,830.00) or thirty-three
percent (33%) of the actual development costs, whichever is
less, for a term of twenty (20) years from the date the
commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission three hundred fifty-one
thousand dollars ($351,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024.
Source notes for subsection (k): (Laws 2019, Ch. 55, § 1.)
(m) Project – Lovell Moncur Lateral Rehabilitation 2019:
(i) Project sponsor: Lovell Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
lateral pipelines and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: Two million six hundred
thirty-seven thousand four hundred two dollars ($2,637,402.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed one million six hundred seventy thousand dollars
($1,670,000.00) or one hundred percent (100%) of the approved
materials costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one million six hundred
seventy thousand dollars ($1,670,000.00) or as much thereof as
is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures.
Source notes for subsection (m): (Laws 2019, Ch. 55, § 1.)
(n) Project – Midvale Irrigation District Rehabilitation
2019:
(i) Project sponsor: Midvale Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
lateral pipelines and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: Eight hundred twenty-six
thousand dollars ($826,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed five hundred fifty-nine thousand dollars ($559,000.00)
or one hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission five hundred fifty-nine
thousand dollars ($559,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures.
Source notes for subsection (n): (Laws 2019, Ch. 55, § 1.)
(o) Project – Shoshone Irrigation District Rehabilitation
2019:
(i) Project sponsor: Shoshone Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
lateral pipelines, structures and appurtenances necessary to
make the project function in the manner intended;
(iv) Total project budget: Five hundred ninety-seven
thousand dollars ($597,000.000);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and as approved by the commission an amount not
to exceed two hundred eighty-two thousand dollars ($282,000.00)
or one hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission two hundred eighty-two
thousand dollars ($282,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2024;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and as approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials and bidding documents and monitor construction
activities including the installation of project components and
the tracking of project expenditures. Source notes
for subsection (o): (Laws 2019, Ch. 55, § 1, 2023, Ch. 180, §
2.)
(p) Project – Wheatland Irrigation District Tunnel Dam
Rehabilitation 2019:
(i) Project sponsor: Wheatland Irrigation District;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction
for rehabilitation of a diversion dam structure and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Five million five hundred
thirty-eight thousand dollars ($5,538,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed three million seven hundred ten
thousand four hundred sixty dollars ($3,710,460.00) or sixty-
seven percent (67%) of the actual development costs, whichever
is less;
(vi) Project loan: The state of Wyoming shall loan to
the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one million eight hundred
twenty-seven thousand five hundred forty dollars ($1,827,540.00)
or thirty-three percent (33%) of the actual development costs,
whichever is less, for a term of fifty (50) years from the date
the commission determines that project benefits accrue to the
sponsor, at an annual interest rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission five million five
hundred thirty-eight thousand dollars ($5,538,000.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2024.
Source notes for subsection (p): (Laws 2020, Ch. 113 § 2.)
(q) Project – Wind River Inter-Tribal Council
Rehabilitation 2019:
(i) Project sponsor: Business council of the Eastern
Shoshone Indian Tribe and business council of the Northern
Arapaho Indian Tribe;
(ii) Project purpose: Agricultural water supply;
(iii) Project description: Design and construction of
canal laterals, control structures and appurtenances necessary
to make the project function in the manner intended;
(iv) Total project budget: One million eight hundred
fifty-eight thousand dollars ($1,858,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed nine hundred twenty-nine
thousand dollars ($929,000.00) or fifty percent (50%) of the
actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission nine hundred twenty-
nine thousand dollars ($929,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2025;
(vii) Special conditions: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources. Source notes for subsection
(q): (Laws 2019, Ch. 55, § 1; 2024, Ch. 99, § 2.)
Nearby Sections
15
Cite This Page — Counsel Stack
Wyoming § 99-3-2406, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/3/99-3-2406.