(a) Authorization is granted for the Level III
rehabilitation construction projects identified in this section,
subject to the general conditions specified in W.S. 99-3-104.
Source notes for subsection (a): (Laws 2011, Ch. 63, § 1.)
(b) Project – Cody Canal Chute:
(i) Project sponsor: Cody Canal Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of a chute and appurtenances necessary to make the project
function in the manner intended;
(iv) Total project budget: Two hundred twenty-three
thousand dollars ($223,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project one hundred forty-nine thousand four hundred ten dollars
($149,410.00) or sixty-seven percent (67%) of the actual
development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed seventy-three thousand five
hundred ninety dollars ($73,590.00) or thirty-three percent
(33%) of actual development costs, whichever is less, for a term
of twenty (20) years from the date the commission determines
project benefits accrue to the sponsor, at an annual rate of
four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission two hundred twenty-
three thousand dollars ($223,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2016.
Source notes for subsection (b): (Laws 2011, Ch. 63, § 1.)
(c) Project – Cody Canal Drop Structure:
(i) Project sponsor: Cody Canal Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of a drop structure and appurtenances necessary to make the
project function in the manner intended;
(iv) Total project budget: One hundred five thousand
dollars ($105,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed fifty thousand dollars ($50,000.00) or one hundred
percent (100%) of the approved materials costs, whichever is
less;
(vi) Appropriation: There is appropriated from water
development account II to the commission fifty thousand dollars
($50,000.00) or as much thereof as is necessary to carry out the
purpose of this subsection. Unexpended funds appropriated under
this subsection shall revert to water development account II on
July 1, 2016;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials bidding documents and monitor construction activities
including the installation of project components and the
tracking of project expenditures.
Source notes for subsection (a): (Laws 2011, Ch. 63, § 1.)
(d) Project – Eden Valley Rehabilitation 2011:
(i) Project sponsor: Eden Valley Irrigation and
Drainage District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction of
rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Three million four hundred
twenty-six thousand dollars ($3,426,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one million seven hundred
thirteen thousand dollars ($1,713,000.00) or fifty percent (50%)
of the actual development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one million seven
hundred thirteen thousand dollars ($1,713,000.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2016;
(vii) Special conditions: The sponsor is responsible
for acquiring fifty percent (50%) of the total project budget
from other sources.
Source notes for subsection (d): (Laws 2011, Ch. 63, § 1.)
(e) Project – Goshen Rehabilitation 2011:
(i) Project sponsor: Goshen Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Three million fifty
thousand dollars ($3,050,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed one million one hundred thousand dollars ($1,100,000.00)
or one hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one million one hundred
thousand dollars ($1,100,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2016;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials bidding documents and monitor construction activities
including the installation of project components and the
tracking of project expenditures.
Source notes for subsection (e): (Laws 2011, Ch. 63, § 1.)
(f) Project – Kirby Rehabilitation 2011:
(i) Project sponsor: Kirby Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Four hundred twenty
thousand dollars ($420,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project two hundred eighty-one thousand four hundred dollars
($281,400.00) or sixty-seven percent (67%) of the actual
development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project an amount not to exceed one hundred thirty-eight
thousand six hundred dollars ($138,600.00) or thirty-three
percent (33%) of actual development costs, whichever is less,
for a term of twenty (20) years from the date the commission
determines project benefits accrue to the sponsor, at an annual
rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission four hundred twenty
thousand dollars ($420,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2017.
Source notes for subsection (f): (Laws 2011, Ch. 63, § 1; 2016,
Ch. 55, §2.)
(g) Project – Little Snake Rehabilitation 2011:
(i) Project sponsor: Savery-Little Snake River Water
Conservancy District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Two hundred thirty
thousand dollars ($230,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project one hundred fifty-four thousand one hundred dollars
($154,100.00) or sixty-seven percent (67%) of the actual
development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission one hundred fifty-four
thousand one hundred dollars ($154,100.00) or as much thereof as
is necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2016;
(vii) Special conditions: The sponsor is responsible
for acquiring thirty-three percent (33%) of the total project
budget from other sources.
Source notes for subsection (g): (Laws 2011, Ch. 63, § 1.)
(h) Project – Midvale Rehabilitation 2011:
(i) Project sponsor: Midvale Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: Six hundred thirty
thousand dollars ($630,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed four hundred fifty thousand dollars ($450,000.00) or one
hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission four hundred fifty
thousand dollars ($450,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2016;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials bidding documents and monitor construction activities
including the installation of project components and the
tracking of project expenditures.
Source notes for subsection (h): (Laws 2011, Ch. 63, § 1.)
(j) Project – Shoshone Rehabilitation 2011:
(i) Project sponsor: Shoshone Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: One million one hundred
seventy thousand dollars ($1,170,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the purchase of project materials as supported by
vendor invoices and approved by the commission an amount not to
exceed five hundred eighty-five thousand dollars ($585,000.00)
or one hundred percent (100%) of the approved materials costs,
whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission five hundred eighty-
five thousand dollars ($585,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2016;
(vii) Special conditions:
(A) The sponsor is responsible for all project
costs with the exception of the purchase of project materials as
supported by vendor invoices and approved by the commission;
(B) The sponsor is responsible for retaining
professional engineering services to design the project, compile
materials bidding documents and monitor construction activities
including the installation of project components and the
tracking of project expenditures.
Source notes for subsection (j): (Laws 2011, Ch. 63, § 1.)
(k) Project – Wheatland Rehabilitation 2011:
(i) Project sponsor: Wheatland Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the irrigation system and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: One million eighty
thousand dollars ($1,080,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, project land
procurement, construction engineering and construction of the
project seven hundred twenty-three thousand six hundred dollars
($723,600.00) or sixty-seven percent (67%) of the actual
development costs, whichever is less;
(vi) Appropriation: There is appropriated from water
development account II to the commission seven hundred twenty-
three thousand six hundred dollars ($723,600.00) or as much
thereof as is necessary to carry out the purpose of this
subsection. Unexpended funds appropriated under this subsection
shall revert to water development account II on July 1, 2016;
(vii) Special conditions: The sponsor is responsible
for acquiring thirty-three percent (33%) of the total project
budget from other sources.
Source notes for subsection (k): (Laws 2011, Ch. 63, § 1.)
(m) Project – Willwood Dam Rehabilitation:
(i) Project sponsor: Willwood Irrigation District;
(ii) Project purpose: Agriculture water supply;
(iii) Project description: Design and construction
of rehabilitation measures for the diversion structure and
appurtenances necessary to make the project function in the
manner intended;
(iv) Total project budget: One million six hundred
twenty thousand dollars ($1,620,000.00);
(v) Project grant: The state of Wyoming shall grant
to the sponsor from water development account II through the
commission for the design, permit procurement, and project land
procurement, construction engineering and construction of the
project one million eighty-five thousand four hundred dollars
($1,085,400.00) or sixty-seven percent (67%) of the actual
development costs, whichever is less;
(vi) Project loan: The state of Wyoming shall loan
to the sponsor from water development account II through the
commission for the design, permit procurement, and project land
procurement, construction engineering and construction of the
project an amount not to exceed five hundred thirty-four
thousand six hundred dollars ($534,600.00) or thirty-three
percent (33%) of actual development costs, whichever is less,
for a term of thirty (30) years from the date the commission
determines project benefits accrue to the sponsor, at an annual
rate of four percent (4%);
(vii) Appropriation: There is appropriated from water
development account II to the commission one million six hundred
twenty thousand dollars ($1,620,000.00) or as much thereof as is
necessary to carry out the purpose of this subsection.
Unexpended funds appropriated under this subsection shall revert
to water development account II on July 1, 2018.
Source notes for subsection (m): (Laws 2011, Ch. 63, § 1; 2012,
Ch. 14, § 2; 2017, Ch. 75, § 2.)
Nearby Sections
15
Cite This Page — Counsel Stack
Wyoming § 99-3-1604, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/3/99-3-1604.