Wyoming Statutes
§ 29-3-111 — Claim against contractor submitted to owner; reduction of subsequent payments to contractor by owner; duty of owner to notify contractor and of contractor to dispute or adjust claim
(a)Every person performing any work or furnishing any
material, as specified in this chapter, under contract whose
demand to be reimbursed for the work done or material furnished
has not been paid shall serve the owner by certified mail return
receipt requested, with an account signed before a notarial
officer of the amount and value of the work performed or the
material furnished remaining unpaid. Thereafter the owner or his
agent shall retain out of any subsequent payments to the
contractors the value of the work performed or material
furnished for the person making the claim.
(b)When notice is served on the owner according to
subsection (a) of this section he shall immediately furnish the
contractor with a copy of the notice.
(c)Within ten (10) days of receipt of the notice required
Free access — add to your briefcase to read the full text and ask questions with AI
Wyoming § 29-3-111 (Claim against contractor submitted to owner; reduction of subsequent payments to contractor by owner; duty of owner to notify contractor and of contractor to dispute or adjust claim) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.