Text
The public utility or utilities report shall set forth an
estimate of the total underground conversion costs for the
district and shall also indicate the cost of underground
conversion of facilities of the public utility located within
the boundaries of the various parcels or lots within the
district. The report shall also contain the public utility's
recommendations concerning the engineering feasibility of the
project for the district proposed insofar as the physical
characteristics of the district are concerned. The report shall
make recommendations by the public utility concerning inclusion
or exclusion of areas within the district or immediately
adjacent to the district. The governing body shall consider the
public utility's recommendations concerning feasibility and may
amend the bou
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 37-13-101
Short title§ 37-13-102
Legislative purpose§ 37-13-103
Definitions§ 37-13-104
Powers conferred§ 37-13-105
Basis of assessments§ 37-13-106
Resolution for cost and feasibility study§ 37-13-107
Costs and feasibility report§ 37-13-112
Waiver of objections§ 37-13-113
Proposed assessment list§ 37-13-114
Proposed assessment resolution§ 37-13-115
Board of equalization and reviewCite This Page — Counsel Stack
Bluebook (online)
Wyoming § 37-13-107, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/13/37-13-107.