§ 35-12-108 — Quantity of water available; analysis; public comment; opinions
Wyoming § 35-12-108
This text of Wyoming § 35-12-108 (Quantity of water available; analysis; public comment; opinions) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Wyo. Stat. Ann. § 35-12-108 (2026).
Text
(a)If an applicant applies for an industrial siting
permit, pursuant to W.S. 35-12-106, or for a waiver of the
application provisions, pursuant to W.S. 35-12-107, for a
facility which requires the use of eight hundred (800) or more
acre feet of the waters of this state annually, the applicant
shall prepare and submit to the state engineer a water supply
and water yield analysis with a request for a preliminary and
final opinion as to the quantity of water available for the
proposed facility.
(b)Within ninety (90) days after the applicant has
submitted an acceptable water supply and yield analysis, the
state engineer, at the applicant's expense, shall complete a
comprehensive review of the water supply and water yield
analysis submitted.
(c)Within five (5) days after completion of the re
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 35-12-101
Short title§ 35-12-102
Definitions§ 35-12-103
Creation of industrial siting division§ 35-12-112
Record of hearing; procedure§ 35-12-114
Review of grant or denial of permit§ 35-12-116
Revocation or suspension of permitCite This Page — Counsel Stack
Bluebook (online)
Wyoming § 35-12-108, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/12/35-12-108.