§ 35-12-108 — Quantity of water available; analysis; public comment; opinions

Wyoming § 35-12-108
JurisdictionWyoming
Title 35Public Health and Safety
Ch. 12INDUSTRIAL DEVELOPMENT AND SITING

This text of Wyoming § 35-12-108 (Quantity of water available; analysis; public comment; opinions) is published on Counsel Stack Legal Research, covering Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyo. Stat. Ann. § 35-12-108 (2026).

Text

(a)If an applicant applies for an industrial siting permit, pursuant to W.S. 35-12-106, or for a waiver of the application provisions, pursuant to W.S. 35-12-107, for a facility which requires the use of eight hundred (800) or more acre feet of the waters of this state annually, the applicant shall prepare and submit to the state engineer a water supply and water yield analysis with a request for a preliminary and final opinion as to the quantity of water available for the proposed facility.
(b)Within ninety (90) days after the applicant has submitted an acceptable water supply and yield analysis, the state engineer, at the applicant's expense, shall complete a comprehensive review of the water supply and water yield analysis submitted.
(c)Within five (5) days after completion of the re

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Wyoming § 35-12-108, Counsel Stack Legal Research, https://law.counselstack.com/statute/wy/12/35-12-108.