§ 70-637 — Construction, repairs, and improvements; contracts; sealed bids; exceptions; notice; when

Nebraska·Ch. 70 Power Districts and Corporations
(1)A district shall cause estimates of the costs to be made by some competent engineer or engineers before the district enters into any contract for:
(a)The construction, reconstruction, remodeling, building, alteration, maintenance, repair, extension, or improvement, for the use of the district, of any:
(i)Power plant or system;
(ii)Hydrogen production, storage, or distribution system;
(iii)Ethanol production or distribution system;
(iv)Irrigation works; or
(v)Part or section of a system or works described in subdivisions (i) through (iv) of this subdivision; or
(b)The purchase of any materials, machinery, or apparatus to be used in the projects described in subdivision (1)(a) of this section.
(2)If the estimated cost exceeds the sum of seven hundred fifty thousand dollars, for t

Free access — add to your briefcase to read the full text and ask questions with AI

Nebraska § 70-637 (Construction, repairs, and improvements; contracts; sealed bids; exceptions; notice; when) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bruno v. Metropolitan Utilities Dist.
287 Neb. 551 (Nebraska Supreme Court, 2014)
9 case citations

Legislative History

Source: Laws 1933, c. 86, § 10, p. 351; C.S.Supp.,1941, § 70-710; Laws 1943, c. 146, § 4, p. 523; R.S.1943, § 70-637; Laws 1955, c. 268, § 1, p. 847; Laws 1959, c. 316, § 6, p. 1161; Laws 1967, c. 423, § 1, p. 1299; Laws 1975, LB 63, § 1; Laws 1981, LB 34, § 2; Laws 1984, LB 152, § 1; Laws 1984, LB 540, § 11; Laws 1986, LB 1230, § 45; Laws 1998, LB 1129, § 2; Laws 1999, LB 566, § 2; Laws 2005, LB 139, § 14; Laws 2007, LB636, § 6; Laws 2008, LB939, § 3; Laws 2009, LB300, § 1; Laws 2024, LB1370, § 3.