Nebraska Statutes
§ 70-1028 — Electric transmission line approved for construction in regional transmission organization transmission plan; notice to board; failure to provide notice; effect
Nebraska § 70-1028
JurisdictionNebraska
Ch. 70Power Districts and Corporations
This text of Nebraska § 70-1028 (Electric transmission line approved for construction in regional transmission organization transmission plan; notice to board; failure to provide notice; effect) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Neb. Rev. Stat. § 70-1028 (2026).
Text
(1)If an electric transmission line has been approved for construction in a regional transmission organization transmission plan, the incumbent electric transmission owner of the existing electric transmission facilities to which the electric transmission line will connect shall give notice to the board, in writing, within ninety days after such approval, if it intends to construct, own, and maintain the electric transmission line. If no notice is provided, the incumbent electric transmission owner shall surrender its first right to construct, own, and maintain the electric transmission line and any other incumbent electric transmission owner may file an application for the electric transmission line under section 70-1012 . Within twenty-four months after such notice, the incumbent elect
Free access — add to your briefcase to read the full text and ask questions with AI
Related
LSP Transmission Holdings, LLC v. Katie Sieben
954 F.3d 1018 (Eighth Circuit, 2020)
Legislative History
Source: Laws 2013, LB388, § 1; Laws 2016, LB824, § 12.
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Nebraska § 70-1028, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/70-1028.