§ 70-1015 — Suppliers; electric generation facilities and transmission lines; unauthorized construction, acquisition, or service; injunction; violation; actions authorized; private electric supplier; commencement of construction prior to providing notice; violation; fine; executive director; powers and duties; dispute; hearing; procedure; decision; costs
Nebraska·Ch. 70 Power Districts and Corporations
(1)If any supplier violates Chapter 70, article 10, by either (a) commencing the construction or finalizing or attempting to finalize the acquisition of any generation facilities, any transmission lines, or any related facilities without first providing notice or obtaining board approval, whichever is required, or (b) serving or attempting to serve at retail any customers located in Nebraska or any wholesale customers in violation of section 70-1002.02 , such construction, acquisition, or service of such customers shall be enjoined in an action brought in the name of the State of Nebraska until such supplier has complied with Chapter 70, article 10.
(2)If the executive director of the board determines that a private electric supplier commenced construction of a privately developed renew
Free access — add to your briefcase to read the full text and ask questions with AI
Nebraska § 70-1015 (Suppliers; electric generation facilities and transmission lines; unauthorized construction, acquisition, or service; injunction; violation; actions authorized; private electric supplier; commencement of construction prior to providing notice; violation; fine; executive director; powers and duties; dispute; hearing; procedure; decision; costs) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Source: Laws 1963, c. 397, § 15, p. 1265; Laws 1967, c. 426, § 1, p. 1302; Laws 1981, LB 181, § 52; Laws 2011, LB208, § 4; Laws 2016, LB824, § 11; Laws 2018, LB1008, § 4; Laws 2019, LB155, § 2; Laws 2025, LB43, § 4. Effective Date: February 26, 2025