Nebraska Statutes
§ 70-1012.01 — Suppliers; electric generation and transmission facilities; terminate construction or acquisition; filing; reasons; hearing; effect; section, how construed
Nebraska § 70-1012.01
JurisdictionNebraska
Ch. 70Power Districts and Corporations
This text of Nebraska § 70-1012.01 (Suppliers; electric generation and transmission facilities; terminate construction or acquisition; filing; reasons; hearing; effect; section, how construed) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Neb. Rev. Stat. § 70-1012.01 (2026).
Text
(1)If a supplier terminates construction or acquisition of electric generation or transmission facilities after receiving approval for the facilities from the board, the supplier shall file with the board, within thirty days after the action taken to terminate construction or acquisition, a statement of the factors or reasons relied upon by the supplier in taking such action. Within ten days after receipt of such a filing, the board shall give notice of the filing to such other suppliers as it deems interested or affected by such action and it shall hold a hearing for the purpose of obtaining such additional information as the board deems advisable or necessary to inform other suppliers and the public of the reasons for such termination. Notice of any such hearing shall be given to those
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Source: Laws 1979, LB 119, § 2; Laws 1981, LB 181, § 50; Laws 2016, LB824, § 6.