Text
Before entering a contract under section 48-05-11, a governmental unit shall submit a
request for proposals. The time period between the request for proposals and the due date for
proposals may be no less than fifteen business days. Upon receipt of the request for proposals,
the governmental unit shall evaluate all proposals from qualified providers which include
estimates of all costs of installations, modifications, or remodeling, including costs of design,
engineering, installation, maintenance, repairs, or debt service, and estimates of the amounts by
which energy or operating costs will be reduced.
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 48-01.2-01
Definitions§ 48-01.2-02.1
Public improvement construction threshold§ 48-01.2-05
Contents of advertisement§ 48-01.2-06
Bid requirements for public improvements§ 48-01.2-07
Opening of bids - Award of contract§ 48-01.2-08
Officers must not be interested in contract§ 48-01.2-09
Contract with successful bidder§ 48-01.2-10
Bonds from contractors for public improvements§ 48-01.2-13
Payments§ 48-01.2-14
Late payment - Rate of interestCite This Page — Counsel Stack
Bluebook (online)
North Dakota § 48-05-10, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/48-05-10.