§ 48-01.2-13 — Payments
North Dakota § 48-01.2-13
This text of North Dakota § 48-01.2-13 (Payments) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
N.D. Cent. Code § 48-01.2-13 (2026).
Text
At least once in each calendar month during the continuance of work upon any public
improvement, the governing body shall receive and consider any partial payment estimate
prepared by the architect or engineer. Upon review and approval, the governing body shall pay
an estimate in an amount equal to the estimated value of the labor and material furnished plus
the material adequately stored. A partial payment estimate must include retentions or retainage
as follows: ten percent of each estimate until the project is fifty percent completed with no
further retainage on estimates during the continuance of the contract unless unsatisfactory
progress or performance is documented. The governing body may, upon completion of
ninety-five percent of the contract, pay to the contractor up to ninety-fiv
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 48-01.2-01
Definitions§ 48-01.2-02.1
Public improvement construction threshold§ 48-01.2-05
Contents of advertisement§ 48-01.2-06
Bid requirements for public improvements§ 48-01.2-07
Opening of bids - Award of contract§ 48-01.2-08
Officers must not be interested in contract§ 48-01.2-09
Contract with successful bidder§ 48-01.2-10
Bonds from contractors for public improvements§ 48-01.2-13
Payments§ 48-01.2-14
Late payment - Rate of interestCite This Page — Counsel Stack
Bluebook (online)
North Dakota § 48-01.2-13, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/48-01.2-13.