1.An agency construction manager, before starting any work, shall provide the governing
body with a bond that is equal to the cost of the agency construction manager's
services with the governing body. Under an agency construction manager delivery
method, each contractor performing services on the public improvement shall provide
the governing body with a separate bond for the contractor's portion of the public
improvement.
2.A construction manager at-risk, before starting any construction, shall provide the
governing body with a bond in an amount at least equal to the amount of the
guaranteed maximum price. The bond must be conditioned to be void if the contractor
and all subcontractors fully perform all terms, conditions, and provisions of the
construction services contract and pay all
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 48-01.2-01
Definitions§ 48-01.2-02.1
Public improvement construction threshold§ 48-01.2-05
Contents of advertisement§ 48-01.2-06
Bid requirements for public improvements§ 48-01.2-07
Opening of bids - Award of contract§ 48-01.2-08
Officers must not be interested in contract§ 48-01.2-09
Contract with successful bidder§ 48-01.2-10
Bonds from contractors for public improvements§ 48-01.2-13
Payments§ 48-01.2-14
Late payment - Rate of interestCite This Page — Counsel Stack
Bluebook (online)
North Dakota § 48-01.2-23, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/48-01.2-23.