North Dakota Statutes

§ 48-01.2-21 — Selection process for construction management at-risk services - Construction services

North Dakota § 48-01.2-21
JurisdictionNorth Dakota
Title 48Public Buildings
Ch. 48-01.2Public Improvement Bids and Contracts

This text of North Dakota § 48-01.2-21 (Selection process for construction management at-risk services - Construction services) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.D. Cent. Code § 48-01.2-21 (2026).

Text

Construction services. After the governing body and the construction manager at-risk have finalized the contract for planning and design phase services and the process has progressed sufficiently to provide the construction manager at-risk the necessary project details, the governing body and the construction manager at-risk shall enter negotiations for a guaranteed maximum price and contract terms for the general construction of the public improvement. If the governing body is unable to negotiate a satisfactory contract with the highest qualified person on the list of finalists, the governing body shall terminate negotiations with that person. The governing body shall commence negotiations with the next most qualified person on the list in sequence until an agreement is reached or a deter

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
North Dakota § 48-01.2-21, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/48-01.2-21.