1.
a.Within six months from July 1, 2025, the owner of a conveyance shall register the
conveyance with the board.
b.The owner of a new elevator or other conveyance must register the conveyance
with the board within thirty days after the conveyance has been inspected and
approved.
c.When registering a conveyance, the owner shall provide to the board the type of
the conveyance, the rated load, the number of landings and speed of the
conveyance, the name of the manufacturer of the conveyance, the location of the
conveyance, the purpose for which the conveyance is used, and any additional
information the board may require.
d.When a conveyance subject to this chapter is decommissioned or otherwise
taken out of service, the owner responsible for the equipment shall notify the
board within s
Free access — add to your briefcase to read the full text and ask questions with AI
1. a. Within six months from July 1, 2025, the owner of a conveyance shall register the
conveyance with the board.
b. The owner of a new elevator or other conveyance must register the conveyance
with the board within thirty days after the conveyance has been inspected and
approved.
c. When registering a conveyance, the owner shall provide to the board the type of
the conveyance, the rated load, the number of landings and speed of the
conveyance, the name of the manufacturer of the conveyance, the location of the
conveyance, the purpose for which the conveyance is used, and any additional
information the board may require.
d. When a conveyance subject to this chapter is decommissioned or otherwise
taken out of service, the owner responsible for the equipment shall notify the
board within six months to request the conveyance be removed from the
registration list.
2. Before an installation or alteration may be commenced on a conveyance, an elevator
contractor shall apply to the board for a permit.
3. An application for a permit must include:
a. A copy of the specifications for the conveyance and must be accurately scaled
and include fully dimensional plans showing the location of the installation in
relation to the plans and elevation of the building.
b. An illustration of each detail of construction and design, including electrical
drawings.
c. The location of the machinery space, machine room, control space, or control
room and the equipment to be installed, relocated, or altered.
d. All structural supporting members of the conveyance, including foundations.
e. A description of the materials to be employed and all loads to be supported or
conveyed.
f. A copy of the written maintenance control program for the conveyance.
4. The elevator contractor shall post the permit at the site of the conveyance while work
is in progress. The elevator contractor obtaining the permit shall be responsible for the
complete scope of work covered by the permit and ensure any alteration is performed
only by a licensed elevator mechanic and performed in accordance the requirements
of this chapter and any rules adopted by the board.