69-5-114 . Review by independent consultant.

(1)If electric facilities providers that have provided cost estimates to a new large customer are unable to reach agreement as to which electric facilities provider can provide electric service facilities at the least cost, an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110 , shall determine which electric facilities provider can extend its line to the new large customer at the least cost. The cost of those engineering services must be paid equally by the electric facilities providers involved.
(2)If elec

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 6, Ch. 231, L. 2007.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Montana § 69-5-114, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/5/69-5-114.