§ 75-26-309 — Release Of Bond -- Use Of Bond By Department
Montana § 75-26-309
JurisdictionMontana
Title 75ENVIRONMENTAL PROTECTION
Ch. 26WIND GENERATION AND SOLAR FACILITIES
Part 3Decommissioning
This text of Montana § 75-26-309 (Release Of Bond -- Use Of Bond By Department) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Mont. Code Ann. § 75-26-309 (2026).
Text
75-26-309 . Release of bond -- use of bond by department.
(1)(a) Subject to subsection (1)(b), the department shall release the bond if it is satisfied that an owner has properly decommissioned a wind generation facility or solar facility in accordance with the plan required in 75-26-304 .
(b)At any time, an owner of a wind generation facility or solar facility may petition the department for release of the bond, and the department shall reply with a determination within 90 days.
(2)If the owner of a wind generation facility or solar facility fails to properly decommission a wind generation facility or solar facility and has not commenced action to rectify deficiencies within 90 days after notification by the department, the department shall cause the bond to be forfeited. The departmen
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
En. Sec. 4, Ch. 247, L. 2017; amd. Sec. 4, Ch. 304, L. 2019.
Nearby Sections
11
§ 75-26-301
Definitions§ 75-26-302
And 75-26-303 Reserved§ 75-26-304
Bond -- Penalty For Failure To Submit§ 75-26-305
Decommissioning Lien§ 75-26-306
And 75-26-307 Reserved§ 75-26-309
Release Of Bond -- Use Of Bond By Department§ 75-26-310
Rulemaking§ 75-26-401
Reserved§ 75-26-402
Required Setback For Wind Turbine GeneratorsCite This Page — Counsel Stack
Bluebook (online)
Montana § 75-26-309, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/26/75-26-309.