§ 75-26-305 — Decommissioning Lien
Montana·Title 75 ENVIRONMENTAL PROTECTION·Ch. 26 WIND GENERATION AND SOLAR FACILITIES·Part 3 Decommissioning
75-26-305 . Decommissioning lien.
(1)For a wind generation facility or solar facility that has not submitted a bond to the department or within 30 days of abandonment of a wind generation facility or solar facility, the department shall file a lien on the generation assets of the facility in an amount not less than the estimated decommissioning costs in the decommissioning plan filed pursuant to 75-26-304 plus an annual inflationary amount determined by the department.
(2)The department shall release a lien secured pursuant to subsection (1) following the receipt and acceptance of a decommissioning bond submitted as required by 75-26-304 (6)(b), (6)(c), or (6)(d).
(3)If the owner of a wind generation facility or solar facility fails to properly decommission a wind generation facility or
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 75-26-305 (Decommissioning Lien) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 2, Ch. 631, L. 2025.
Nearby Sections
11
§ 75-26-301
Definitions§ 75-26-302
And 75-26-303 Reserved§ 75-26-304
Bond -- Penalty For Failure To Submit§ 75-26-305
Decommissioning Lien§ 75-26-306
And 75-26-307 Reserved§ 75-26-309
Release Of Bond -- Use Of Bond By Department§ 75-26-310
Rulemaking§ 75-26-401
Reserved§ 75-26-402
Required Setback For Wind Turbine Generators