Massachusetts Statutes

§ 75G — Marking of location of underground line

Massachusetts § 75G
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title XXIICORPORATIONS
Ch. 164MANUFACTURE AND SALE OF GAS AND ELECTRICITY

This text of Massachusetts § 75G (Marking of location of underground line) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 164, § 75G (2026).

Text

Section 75G. Any natural gas pipe line company which lays pipes or other underground equipment or structures on any land on which it does not have a fee, shall, within sixty days after laying such pipe, equipment or structure, mark on the land, in such manner as not to interfere with the use of such land, the actual location of such pipe, equipment or structure and furnish the owner of the land, within thirty days after the owner makes a written request therefor, with an accurate plan, suitable for recording or registration, showing the exact location of the pipe line easement with reference to the bounds and boundaries of the land. This obligation shall be specifically enforceable in equity by the supreme judicial or superior court upon application of the owner of the land, and in such pr

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

9
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 75G, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/164/75G.