§ 8-23-9-30 — Claims against contractors; notice of rejection; commencement of actions

Indiana § 8-23-9-30
JurisdictionIndiana
Art. 23INDIANA DEPARTMENT OF
Ch. 9State Highway Contracts; General Powers

This text of Indiana § 8-23-9-30 (Claims against contractors; notice of rejection; commencement of actions) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-23-9-30 (2026).

Text

If a claim is rejected in whole or in part, the department shall immediately notify the claimant of the action by certified mail. Within ninety (90) days after receiving notice of a rejection the claimant must commence an action against the contractor or the surety on the bond in a court of competent jurisdiction to recover the amount of the claim. Upon the filing of an action, the claimant shall procure a certificate from the clerk of the court under the seal of office that the action has been filed and listing the date of filing and the parties. The claimant shall promptly forward the certificate to the department.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.18-1990, SEC.218.