§ 8-23-9-25 — Nonperformance or abandonment of contracts; completion of work; costs and expenses

Indiana·Art. 23 INDIANA DEPARTMENT OF·Ch. 9 State Highway Contracts; General Powers

Any time a contractor:

(1)fails to commence or carry forward;
(2)improperly performs;
(3)has abandoned; or
(4)fails or refuses to complete; a contract executed under this chapter, the commissioner may relet the work or may complete the work. The commissioner shall deduct the cost and expense from any money that may be due the contractor, and if there is not sufficient money due the contractor to pay for the work, the commissioner shall require the bondsmen to pay for it. The attorney general shall prosecute suit in the name of the state for the collection of the payment under this section.

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 8-23-9-25 (Nonperformance or abandonment of contracts; completion of work; costs and expenses) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Averitt Express, Inc. v. State of Indiana ex rel. Indiana Department of Transportation
18 N.E.3d 608 (Indiana Court of Appeals, 2014)
5 case citations

Legislative History

As added by P.L.18-1990, SEC.218.