§ 8-23-9-18 — Final payments; disputes
Indiana § 8-23-9-18
This text of Indiana § 8-23-9-18 (Final payments; disputes) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-23-9-18 (2026).
Text
(a)Each contract entered into under this
chapter must provide for final payment within one hundred eighty
(180)days after final acceptance of the contract. However, final
payment may not be made on any amount that is in dispute or the
subject of a pending claim, but final payment may be made on that part
of a contract or those amounts that are not in dispute or the subject of
a pending claim. Partial payment does not constitute a bar, an
admission, or estoppel or have any other effect as to those payments in
dispute or the subject of a pending claim.
(b)For the purpose of this section, a dispute exists when the
contractor makes any claim for increase or decrease to any part of the
contract or seeks additional compensation for any reason.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.18-1990, SEC.218.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-23-9-18, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-23-9-18.