§ 8-23-9-16 — Acceptance of completed work; relief of contractor's liability
(a)After complete inspection has been made
and it is determined that the work has been done according to plans and
specifications, the commissioner of the department may approve and
accept completed work in sections of not less than one (1) mile unless
otherwise permitted by the contract documents.
(b)When a section of the work has been completed and accepted,
the contractor is as fully relieved of all liability for the maintenance,
reconstruction, or restoration of the section of the work completed and
accepted, or a part of the work, as the contractor would be if the entire
contract were finally completed and accepted.
(c)If the contract consists of two (2) or more projects as defined by
the department, the commissioner may approve and accept the work of
a completed project, and the c
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 8-23-9-16 (Acceptance of completed work; relief of contractor's liability) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
As added by P.L.18-1990, SEC.218.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
Repealed