§ 8-23-1-40.5 — "Substantial completion"

Indiana § 8-23-1-40.5
JurisdictionIndiana
Art. 23INDIANA DEPARTMENT OF
Ch. 1Definitions

This text of Indiana § 8-23-1-40.5 ("Substantial completion") is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-23-1-40.5 (2026).

Text

5."Substantial completion" refers to the date, as determined by the department, when the construction of the contract is sufficiently completed in accordance with the plans and specifications, as modified by any change orders, so that the construction can be used for its intended purpose.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.117-1995, SEC.1.