Indiana Statutes
§ 8-15.5-5-6.1 — Public-private agreements; actions to facilitate completion
Indiana § 8-15.5-5-6.1
JurisdictionIndiana
Art. 15.5PUBLIC-PRIVATE AGREEMENTS FOR TOLL
Ch. 5Terms and Conditions of Public-Private Agreements
This text of Indiana § 8-15.5-5-6.1 (Public-private agreements; actions to facilitate completion) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-15.5-5-6.1 (2026).
Text
1.
(a)If a public-private agreement is
terminated or the authority exercises its right or remedies under the
public-private agreement with respect to the project before the
completion of the construction, reconstruction, improvement,
extension, or expansion of the project as specified by the public-private
agreement, the authority, subject to subsection (b), may take any or all
of the following actions in order to facilitate completion of the project:
(1)Employ or contract with contractors, subcontractors, suppliers,
architects, engineers, and such other advisers, consultants, and
agents as may be necessary in its judgment to complete the
project, and to fix their compensation.
(2)Contract with or enter into a public-private agreement with a
new operator, and to fix its compensation.
(3
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.218-2017, SEC.75. Amended by P.L.189-2018,
SEC.92.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-15.5-5-6.1, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-15.5-5-6.1.