§ 8-1-8.7-8 — Review of completed construction; costs exceeding estimated and approved costs
Indiana § 8-1-8.7-8
This text of Indiana § 8-1-8.7-8 (Review of completed construction; costs exceeding estimated and approved costs) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-1-8.7-8 (2026).
Text
A public utility may elect to forgo any
commission review of the construction and cost until completion of the
clean coal technology system. If the commission has annually approved
the continuing need for the project under section 5 of this chapter, and
to the extent the public utility seeks to add to the rate base an amount
that does not exceed that filed under section 4(a) of this chapter, the
inclusion of that amount may be challenged only on the basis of
inadequate quality controls. However, inclusion of costs in excess of
those approved by the commission under section 4(b)(2) of this chapter
is not permitted unless the public utility shows those costs to be
necessary and prudent.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.105-1989, SEC.4.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-1-8.7-8, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-8.7-8.