This text of Indiana § 8-1-8.7-4 (Hearings and requisite findings; estimated costs; use of Indiana coal) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-1-8.7-4 (2026).
Text
(a)As a condition for receiving the certificate
required under section 3 of this chapter, an applicant must file an
estimate of the cost of constructing, implementing, and using clean coal
technology and supportive technical information in as much detail as
the commission requires.
(b)The commission shall hold a public hearing on each application.
A certificate shall be granted only if the commission has:
(1)made a finding that the public convenience and necessity will
be served by the construction, implementation, and use of clean
coal technology;
(2)approved the estimated costs;
(3)made a finding that the facility where the clean coal
technology is employed:
(A)utilizes and will continue to utilize Indiana coal as its
primary fuel source; or
(B)is justified, because of economic co
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.105-1989, SEC.4.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-1-8.7-4, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-8.7-4.