§ 8-1-8.5-6 — Review of construction; force and effect of certificate approved under review; election to defer review

Indiana § 8-1-8.5-6
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 8.5Electric Utility Resource Planning and Certification

This text of Indiana § 8-1-8.5-6 (Review of construction; force and effect of certificate approved under review; election to defer review) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-8.5-6 (2026).

Text

(a)In addition to the review of the continuing need for the facility under construction prescribed in section 5.5 of this chapter, the commission shall, at the request of the public utility, maintain an ongoing review of such construction as it proceeds. The applicant shall submit each year during construction, or at such other periods as the commission and the public utility mutually agree, a progress report and any revisions in the cost estimates for the construction.
(b)If the commission approves the construction and the cost of the portion of the facility under review, the certificate shall remain in full force and effect.
(c)If the commission disapproves of all or part of the construction or cost of the portion of the facility under review, the commission may modify or revoke the c

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.12; P.L.53-1992, SEC.6.