Indiana Statutes

§ 8-1-7.9-23 — Petition for approval of project to serve large load customer; required information; case in chief; notice of filing

Indiana § 8-1-7.9-23
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 7.9Expedited Generation Resource Plans and Large Load

This text of Indiana § 8-1-7.9-23 (Petition for approval of project to serve large load customer; required information; case in chief; notice of filing) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-7.9-23 (2026).

Text

(a)This section applies to an energy utility that petitions the commission for approval of a project to serve a large load customer.
(b)In a petition under this section, an energy utility must include, at a minimum, the following:
(1)The energy utility's complete case in chief, which must include, at a minimum, the following:
(A)An agreement from the large load customer that describes the financial assurances:
(i)that afford protections for the energy utility's existing and future customers; and
(ii)to which the large load customer has committed regardless of whether the large load customer ultimately takes service in the anticipated amount and within the anticipated time frame.
(B)A description of:
(i)the demand side management and self-generation options reviewed with the large l

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.217-2025, SEC.2.