Indiana Statutes

§ 8-1-7.9-22 — Petition for approval of project to serve large load customer; requirements for submission; financial assurances by large load customer; projects serving multiple locations or customers

Indiana § 8-1-7.9-22
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 7.9Expedited Generation Resource Plans and Large Load

This text of Indiana § 8-1-7.9-22 (Petition for approval of project to serve large load customer; requirements for submission; financial assurances by large load customer; projects serving multiple locations or customers) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-7.9-22 (2026).

Text

(a)This section applies to an energy utility that petitions the commission for approval of a project to serve a large load customer.
(b)An energy utility may submit to the commission a petition for approval of a project to serve a large load customer only if the following are satisfied:
(1)The petition concerns serving the energy needs of a large load customer.
(2)The large load customer commits to significant and meaningful financial assurances that must:
(A)include reimbursement by the large load customer of at least eighty percent (80%) of the project costs reasonably allocable to the large load customer; and
(B)afford protections for the energy utility's existing and future customers from project costs reasonably allocable to the large load customer regardless of whether the larg

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.217-2025, SEC.2.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 8-1-7.9-22, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-7.9-22.