This text of Indiana § 8-1-7.9-21 (Generation resource submittal; commission's final order; time frame for issuance) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-7.9-21 (2026).

Text

(a)This section applies to an energy utility that submits to the commission for approval a generation resource submittal in accordance with an approved EGR plan.
(b)Notwithstanding IC 8-1-8.5 or any other statute, the commission may approve an energy utility's generation resource submittal to construct, purchase, lease, or otherwise acquire generation resources under this chapter for purposes of meeting the needs of the energy utility's customers. The commission shall make its decision based solely on whether the submittal meets the criteria and requirements set forth in the energy utility's approved EGR plan.
(c)The commission may:
(1)approve the energy utility's generation resource submittal in its entirety;
(2)deny the energy utility's generation resource submittal in its entirety;

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.217-2025, SEC.2.