§ 8-1-7.9-19 — Petition for approval of EGR plan; commission's final order; time frame for issuance

Indiana § 8-1-7.9-19
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 7.9Expedited Generation Resource Plans and Large Load

This text of Indiana § 8-1-7.9-19 (Petition for approval of EGR plan; commission's final order; time frame for issuance) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-7.9-19 (2026).

Text

(a)This section applies to an energy utility that petitions the commission for approval of an EGR plan.
(b)Notwithstanding IC 8-1-8.5 or any other statute, the commission may approve an energy utility's EGR plan to construct, purchase, lease, or otherwise acquire generation resources under this chapter for purposes of meeting the needs of the energy utility's customers. The commission shall make its decision based on whether the relief requested is just, reasonable, and in the public interest.
(c)The commission may:
(1)approve the energy utility's petition in its entirety;
(2)deny the energy utility's petition in its entirety; or
(3)modify the petition, subject to the energy utility's acceptance of the modification.
(d)The commission shall issue a final order on the petition not lat

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.217-2025, SEC.2.