§ 8-1-7.9-18 — Petition for approval of EGR plan; required information

Indiana § 8-1-7.9-18
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 7.9Expedited Generation Resource Plans and Large Load

This text of Indiana § 8-1-7.9-18 (Petition for approval of EGR plan; required information) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-7.9-18 (2026).

Text

(a)This section applies to an energy utility that petitions the commission for approval of an EGR plan.
(b)An energy utility may file a petition with the commission for approval of an EGR plan to acquire generation resources to meet the extraordinary needs for electricity by the energy utility's customers.
(c)In a petition under this section, an energy utility must do the following:
(1)Describe the energy utility's EGR plan for acquiring generation resources to meet the anticipated extraordinary growth in the load of its customers.
(2)Demonstrate a need for generation capacity that exceeds the lesser of:
(A)five percent (5%) of the energy utility's average peak demand over the most recent three (3) calendar years; or
(B)one hundred fifty (150) megawatts.
(3)Provide a load growth fo

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.217-2025, SEC.2.