Indiana Statutes
§ 8-1-7.9-18 — Petition for approval of EGR plan; required information
Indiana § 8-1-7.9-18
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 7.9Expedited Generation Resource Plans and Large Load
This text of Indiana § 8-1-7.9-18 (Petition for approval of EGR plan; required information) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-1-7.9-18 (2026).
Text
(a)This section applies to an energy utility
that petitions the commission for approval of an EGR plan.
(b)An energy utility may file a petition with the commission for
approval of an EGR plan to acquire generation resources to meet the
extraordinary needs for electricity by the energy utility's customers.
(c)In a petition under this section, an energy utility must do the
following:
(1)Describe the energy utility's EGR plan for acquiring
generation resources to meet the anticipated extraordinary growth
in the load of its customers.
(2)Demonstrate a need for generation capacity that exceeds the
lesser of:
(A)five percent (5%) of the energy utility's average peak
demand over the most recent three (3) calendar years; or
(B)one hundred fifty (150) megawatts.
(3)Provide a load growth fo
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.217-2025, SEC.2.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-1-7.9-18, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-7.9-18.