Indiana Statutes

§ 8-1-7.9-12 — "Planning costs"

Indiana § 8-1-7.9-12
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 7.9Expedited Generation Resource Plans and Large Load

This text of Indiana § 8-1-7.9-12 ("Planning costs") is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-7.9-12 (2026).

Text

(a)As used in this chapter, "planning costs" means costs:
(1)incurred or to be incurred by an energy utility before the issuance of an order by the commission under this chapter; and
(2)related to an acquisition or project.
(b)The term includes study, analysis, pre-engineering, engineering, legal, financing, and regulatory costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.217-2025, SEC.2.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 8-1-7.9-12, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-7.9-12.