§ 8-1-44-10 — "Project development costs"
Indiana § 8-1-44-10
This text of Indiana § 8-1-44-10 ("Project development costs") is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-1-44-10 (2026).
Text
As used in this chapter, "project development costs" means costs that have been incurred, or are reasonably estimated to be incurred, in the development of one (1) or more SMRs under the program, including:
(1)evaluation, design, and engineering costs;
(2)costs for federal approvals and licensing;
(3)costs for environmental analyses and permitting;
(4)early site permit (as defined in 10 CFR 52.1) costs;
(5)equipment procurement costs; and
(6)authorized carrying costs.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
§ 52.1
10 C.F.R. § 52.1
Legislative History
As added by P.L.137-2025, SEC.1.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-1-44-10, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-44-10.