Indiana Statutes
§ 8-1-40-21 — Commission's net metering and interconnection rules; application to distributed generation; permitted changes to rules
(a)Subject to subsection (b) and sections 10
and 11 of this chapter, after June 30, 2017, the commission's rules and
standards set forth in:
(1)170 IAC 4-4.2 (concerning net metering); and
(2)170 IAC 4-4.3 (concerning interconnection);
remain in effect and apply to net metering under an electricity
supplier's net metering tariff and to distributed generation under this
chapter.
(b)After June 30, 2017, the commission may adopt changes under
IC 4-22-2 to the rules and standards described in subsection (a) only as
necessary to:
(1)update fees or charges;
(2)adopt revisions necessitated by new technologies; or
(3)reflect changes in safety, performance, or reliability standards.
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 8-1-40-21 (Commission's net metering and interconnection rules; application to distributed generation; permitted changes to rules) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
As added by P.L.264-2017, SEC.6. Amended by P.L.93-2024,
SEC.73.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
Repealed