This text of Indiana § 8-1-40-16 (Electricity supplier's petition for rate for excess distributed generation; annual submission of updated rate) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-40-16 (2026).

Text

Not later than March 1, 2021, an electricity supplier shall file with the commission a petition requesting a rate for the procurement of excess distributed generation by the electricity supplier. After an electricity supplier's initial rate for excess distributed generation is approved by the commission under section 17 of this chapter, the electricity supplier shall submit on an annual basis, not later than March 1 of each year, an updated rate for excess distributed generation in accordance with the methodology set forth in section 17 of this chapter.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.264-2017, SEC.6.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 8-1-40-16, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-40-16.