§ 8-1-39-12 — Commission hearing and order on TDSIC petition; examination by utility consumer counselor and intervenors; new projects or improvements

Indiana § 8-1-39-12
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 39Transmission, Distribution, and Storage System

This text of Indiana § 8-1-39-12 (Commission hearing and order on TDSIC petition; examination by utility consumer counselor and intervenors; new projects or improvements) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-39-12 (2026).

Text

(a)Not more than one hundred twenty (120) days after a public utility files a petition under section 9 of this chapter, the commission shall conduct a hearing and issue an order on the petition.
(b)Not more than sixty (60) days after a public utility files a petition under section 9 of this chapter, the office of the utility consumer counselor and other intervenors, if any, may:
(1)examine the information of the public utility to confirm that the proposed transmission, distribution, and storage system improvements comply with this chapter; and
(2)report its findings to the commission.
(c)If the commission determines that the petition satisfies the requirements of this chapter and the capital expenditures and TDSIC costs are reasonable, the commission shall approve the petition, includ

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.6.