§ 8-1-38-7 — Authority to operate; findings

Indiana § 8-1-38-7
JurisdictionIndiana
Art. 1UTILITIES GENERALLY
Ch. 38Transmission Reliability

This text of Indiana § 8-1-38-7 (Authority to operate; findings) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-38-7 (2026).

Text

(a)The commission shall grant a new electric transmission owner authority to operate as a public utility in Indiana if the commission makes the following findings:
(1)The new electric transmission owner has the financial, managerial, and technical capability to construct, own, operate, and maintain an electric transmission facility.
(2)The new electric transmission owner has the ability and intent to comply with all statutes, rules, and regulations enforced by the commission.
(3)The new electric transmission owner has the intent to construct, own, operate, and maintain an electric transmission facility that is under consideration by an applicable regional transmission organization.
(4)The new electric transmission owner has provided written notice of its request for authority under th

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.174-2013, SEC.1.