This text of Indiana § 8-1-30.9-9 (Water utility's recovery of costs incurred; inclusion in rate base or revenue requirement; completed construction; cancellation of project; construction subject to subsequent review; limitation on recovery of costs exceeding estimate) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-30.9-9 (2026).

Text

Absent fraud, concealment, or gross mismanagement, a water utility shall recover through rates the actual costs the water utility has incurred in reliance on a certificate issued under this chapter as follows:

(1)If construction of a long haul water pipeline has been subject to ongoing review under section 8(a) of this chapter and the commission finds the construction of the long haul water pipeline has been completed, the costs of construction approved by the commission during the ongoing review shall be included, without further commission review, in:
(A)the water utility's rate base, in the case of a public utility; or
(B)the water utility's revenue requirement for extensions and replacements expense, depreciation expense, or debt service expense, as applicable, in the case of a:
(i)

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.99-2025, SEC.1.