§ 8-1-27-13 — Revised cost and schedule estimate for developing and implementing plan; submission to commission
Indiana § 8-1-27-13
This text of Indiana § 8-1-27-13 (Revised cost and schedule estimate for developing and implementing plan; submission to commission) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 8-1-27-13 (2026).
Text
(a)If a public utility makes a substantial
change in a cost and schedule estimate for developing and
implementing an environmental compliance plan or a modified
environmental compliance plan after the estimate has been approved
by the commission under this chapter, the public utility shall file with
the commission for the commission's review and approval the revised
cost and schedule estimate.
(b)To the extent the commission approves a revised cost and
schedule estimate, the estimate shall be the approved cost and schedule
estimate for the plan.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Alliance for Clean Coal v. Bayh
888 F. Supp. 924 (S.D. Indiana, 1995)
Legislative History
As added by P.L.76-1991, SEC.1.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
RepealedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 8-1-27-13, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/8-1-27-13.