Indiana Statutes
§ 8-1-26-20 — Duties of excavator; facilities in or under pavement; use of mechanized equipment; civil penalties
(a)In addition to the notice required in
section 16 of this chapter, a person responsible for an excavation or
demolition operation under section 14 of this chapter shall do all of the
following:
(1)Plan the excavation or demolition to avoid damage to or
minimize interference with underground facilities in and near the
construction area.
(2)Maintain a clearance between an underground facility, as
marked by the operator, and the cutting edge or point of
mechanized equipment equal to the tolerance zone of the physical
plant. If the clearance is less than two (2) feet, or if an
underground facility is located or contained in or under pavement
or another manmade hard surface, exposure of the underground
facility may be accomplished only as follows:
(A)Only by the use of:
(i)hand excavatio
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 8-1-26-20 (Duties of excavator; facilities in or under pavement; use of mechanized equipment; civil penalties) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
MCI, LLC v. Patriot Engineering & Environmental, Inc.
487 F. Supp. 2d 1029 (S.D. Indiana, 2007)
AT&T v. Atlas Excavating, Inc.
(Indiana Court of Appeals, 2013)
Legislative History
As added by P.L.69-1990, SEC.2. Amended by P.L.62-2009,
SEC.17; P.L.200-2014, SEC.6; P.L.53-2024, SEC.10.
Nearby Sections
15
§ 8-1-1-11
Staff of commission§ 8-1-1-12
Repealed§ 8-1-1-13
Repealed§ 8-1-1-14
Annual report§ 8-1-1-15
Implementing rules; duration§ 8-1-1-16
Commission to consider effect of governmental requirements upon
utility's operational expenses§ 8-1-1-4
Repealed§ 8-1-1-4.1
Payment of expenses§ 8-1-1-6
Repealed