This text of Indiana § 8-1-26-16.5 (Design information notice; duty to perform white lining; timing; association's duties on receipt; commencement of work; design information notice contents; operator's duties on receipt; grounds for rejection; effect) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 8-1-26-16.5 (2026).

Text

5.

(a)A person responsible for:
(1)a construction project; or
(2)any other project or operation; that will involve an excavation or demolition operation described in section 14 of this chapter may voluntarily, before commencing preliminary engineering studies or construction planning activities in the project area that will be affected by the excavation or demolition, serve a design information notice on the association of the person's intent to conduct the preliminary engineering studies or construction planning activities. However, not more than two (2) design information notices for the same project and from the same person or source may be submitted in any given one hundred eighty (180) day period.
(b)A person that serves a design information notice on the association under this se

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.122-2017, SEC.4. Amended by P.L.53-2024, SEC.6.