§ 4-13.6-7-8 — Final settlement with contractor

Indiana § 4-13.6-7-8
JurisdictionIndiana
Art. 13.6STATE PUBLIC WORKS
Ch. 7Bonding, Escrow, and Retainages

This text of Indiana § 4-13.6-7-8 (Final settlement with contractor) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 4-13.6-7-8 (2026).

Text

(a)Except for amounts withheld:
(1)from the contractor under section 3 of this chapter for uncompleted minor items; and
(2)under subsection (b); the division may make a full, final, and complete settlement with a contractor, including providing for full payment of all escrowed principal and escrowed income, not later than sixty-one (61) days following the date of substantial completion if the contractor has materially fulfilled all of its obligations under the public works contract.
(b)If the division receives a claim from a subcontractor or a supplier under section 9 of this chapter, the division shall withhold the amount of the claim until the claim is resolved under section 9(c) of this chapter.
(c)After the division makes a final settlement with a contractor, all claims by subcont

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.24-1985, SEC.7. Amended by P.L.75-2012, SEC.2.