§ 4-13.6-7-4 — Payment of subcontractors and suppliers; certification of previous payments; incorrect certification

Indiana § 4-13.6-7-4
JurisdictionIndiana
Art. 13.6STATE PUBLIC WORKS
Ch. 7Bonding, Escrow, and Retainages

This text of Indiana § 4-13.6-7-4 (Payment of subcontractors and suppliers; certification of previous payments; incorrect certification) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 4-13.6-7-4 (2026).

Text

(a)Within ten (10) days of receipt of any payment by the state or the escrow agent, the contractor or escrow agent shall pay each subcontractor and each supplier the appropriate share of the payment the contractor received based upon the service performed by the subcontractor or the materials received from the supplier.
(b)The contractor shall furnish to the division a sworn statement or certification at the time of payment to it that all subcontractors and suppliers have received their share of the previous payment to the contractor.
(c)If a contractor makes an incorrect certification, the department may do any of the following:
(1)Consider the incorrect certification a breach of contract and do any of the following:
(A)Cancel the contract.
(B)Collect from the contractor all funds p

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.24-1985, SEC.7. Amended by P.L.5-1993, SEC.12.