Indiana Statutes

§ 4-13.6-7-3 — Amount of retainage withheld

Indiana § 4-13.6-7-3
JurisdictionIndiana
Art. 13.6STATE PUBLIC WORKS
Ch. 7Bonding, Escrow, and Retainages

This text of Indiana § 4-13.6-7-3 (Amount of retainage withheld) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 4-13.6-7-3 (2026).

Text

(a)To determine the amount of retainage to be withheld, the division shall elect one (1) of the following options:
(1)To withhold no more than six percent (6%) of the dollar value of all work satisfactorily completed until the public work is fifty percent (50%) complete, and nothing further after that.
(2)To withhold no more than three percent (3%) of the dollar value of all work satisfactorily completed until the public work is substantially complete.
(b)Upon substantial completion of the work, the division shall withhold the following:
(1)If there are any remaining uncompleted minor items, until those items are completed, an amount equal to two hundred percent (200%) of the value of each item as determined by the architect-engineer.
(2)Any amounts required to be withheld under sect

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.24-1985, SEC.7. Amended by P.L.75-2012, SEC.1.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 4-13.6-7-3, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/4-13.6-7-3.