§ 4-13.6-3-4 — Increased compensation for early performance of contracts; deductions for late completion of contracts; notice
Indiana § 4-13.6-3-4
This text of Indiana § 4-13.6-3-4 (Increased compensation for early performance of contracts; deductions for late completion of contracts; notice) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 4-13.6-3-4 (2026).
Text
(a)The commissioner may specify in a
contract that early performance of the contract will result in increased
compensation at either:
(1)a percentage of the contract amount; or
(2)a specific dollar amount;
determined by the commissioner.
(b)The commissioner may specify in a contract that completion of
the contract after the termination date of the contract will result in a
deduction from the compensation in the contract at either:
(1)a percentage of the contract amount; or
(2)a specific dollar amount;
determined by the commissioner.
(c)Notice of inclusion of contract provisions permitted under this
section in a contract must be included in the solicitation.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.5-1993, SEC.10.
Nearby Sections
15
§ 4-1-1-1
Dates beginning and ending§ 4-1-1-2
Reports to governor§ 4-1-10-1
Applicability§ 4-1-10-1.5
"Person"§ 4-1-10-11
Attorney general investigation of disclosures; notice to county
prosecutor and state police§ 4-1-10-12
Attorney general determination of infraction; report to appointing
authority and county prosecutor§ 4-1-10-13
Attorney general rulemaking authority§ 4-1-10-2
"State agency"§ 4-1-10-3
Nondisclosure of Social Security number§ 4-1-10-6
State agency complianceCite This Page — Counsel Stack
Bluebook (online)
Indiana § 4-13.6-3-4, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/4-13.6-3-4.