(a)Estimated project costs submitted under
section 3(b)(5) of this chapter must include the following:
(1)Eligible project costs.
(2)Ineligible project costs.
(b)Project costs that are ineligible for grant funding may not be
used to fulfill a grantee's match requirement. A grantee is responsible
for all project costs except the costs funded by a grant.
(c)Ineligible project costs include the following:
(1)Costs incurred before the approval of a grant.
(2)Costs incurred more than twenty-four (24) months after a
grant has been accepted.
(3)Costs incurred by a grantee that exceed original estimated
eligible project costs indicated in a grant application.
(4)Other costs that are not specifically related to a project as
determined by the department.
(d)Eligible project costs may be:
(
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 13-20-20-4 (Project costs) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
As added by P.L.1-1996, SEC.10. Amended by P.L.237-1999,
SEC.6.
Nearby Sections
15
§ 13-11-1-1
Applicability of definitions in this article§ 13-11-1-2
Applicability of definitions in IC 36-1-2§ 13-11-2-0.1
Application of certain amendments to chapter§ 13-11-2-0.2
Application of certain amendments to prior law§ 13-11-2-0.3
"Aboveground petroleum storage tank"§ 13-11-2-0.4
"Aboveground storage tank"§ 13-11-2-0.5
Repealed§ 13-11-2-0.6
Repealed§ 13-11-2-0.7
"ABS sensor"§ 13-11-2-1
"Active area"§ 13-11-2-1.5
"Acute hazardous waste"§ 13-11-2-10
"Asbestos"§ 13-11-2-100
"Hazardous waste facility"§ 13-11-2-101
"Hazardous waste landfill"